On Tuesday, June 28th a crew will be in to level off the parking area and fill voids left by the concrete crew. This may mean additional equipment using the entrance off Prospect and the area between the church and the middle school. On Wednesday, June 29th another crew will be in with lots of equipment prepping the lot for a base-coat of asphalt which will be applied on Thursday. Friday they will paint. I realize VBS is in full swing but as a reminder there is parking on Prospect and between the church and office building as well as between the office building and the playground. The drive in front of the church can also be used the way it is during the weekends, just leave a path along the church side for vehicles. Extra caution will be needed when kids go from the Abbey to the school and back. Thank you, Mr. Earl